Watch as the huge H25 module is lifted on board, performed the huge “monster” Saipem 7000.
The 577 tonne heavy H25 module was installed only six days after leaving the Aibel yard in Haugesund.
The actual lift was performed by the heavy lift vessel Saipem 7000 .
The H25 module is a MEG and Methanol utility module to the main process module M40.
The video is presented by DVA topside manager, Roy Padgett.