AKER Solutions has been awarded a £34.7million contract by StatoilHydro for the delivery of a complete work-over system for subsea trees at the challenging Kristin field in the Norwegian Sea.
The scope of work includes engineering, procurement, manufacturing and testing of a complete work-over intervention system, including tools.
A work-over system is equipment that is needed to perform well-intervention activities on subsea wells. The objective of work-over operations is to maintain and increase production from the subsea wells.
The contract is a call-off from the frame agreement signed between StatoilHydro and Aker Solutions in Q3 2007. This is the third work-over system Aker Solutions will be delivering to StatoilHydro’s Kristin field, which is a high-pressure/high-temperature (HP/HT) field with temperatures up to 180C and pressures up to 15,000psi.