Europe’s ambitious timetable for building its way out of a dependence on Russian energy faces potential delays and billions of dollars in extra costs as the war in Ukraine makes steel, copper and aluminium scarce and more expensive.
A rush to replace Russian fossil fuels is prompting the continent to focus on shoring up flows of liquefied natural gas (LNG) in the near term and increasing generation from renewable sources by 2030. Germany pledges to build two LNG terminals, France wants to resume talks with Spain about a connecting pipeline, and the UK seeks more homegrown wind, solar and nuclear power.
Yet prices for the necessary materials keep heading in one direction. Steel, copper and aluminium each touched records in the past 12 months, and the Bloomberg Commodity Spot Index jumped 46% during the same period. The spikes threaten to slow such undertakings as the European Union’s blueprint to almost triple wind and solar capacity this decade — a colossal investment that could require about 52 million tons of steel alone.
“This war has an impact, of course, on all those companies, including us, that are on the doorstep of making quite large-sized investments,” said Fred van Beers, chief executive officer of SIF Holding NV, which makes steel platforms for wind turbines. “It’s putting our business case upside down.”
Before the invasion, Russian gas was relatively cheap, easy to transport and in ample supply. Those factors, plus the anticipated opening of the Nord Stream 2 pipeline to Germany, helped persuade Europe to reduce its own production and start shuttering coal plants and nuclear reactors to focus on cleaner sources.
The EU imported about 155 billion cubic meters of gas from Russia last year, according to the International Energy Agency. In the aftermath of war, the bloc wants to cut dependency by two-thirds this year.
Higher Costs
About 30 billion cubic meters can be replaced by other suppliers, with the difference made up by renewables, nuclear and changes in consumption, the IEA said. For the EU, the sticker price for the infrastructure may be as much as 20% higher than before the war started, said Grant Sporre, an analyst at Bloomberg Intelligence.
“The build-out is going to be more expensive than governments intended,” Sporre said. “We may see some projects being delayed as prices stay elevated.”
The European Commission’s transition plan involves installing 290 gigawatts of wind and 250 gigawatts of solar. The bill just for the steel amounts to 65 billion euros ($72 billion) at current market prices.
Russia and Ukraine are among the biggest exporters of steel slabs used in building turbines and gas pipelines. While alternative sources are possible, costs for those are 50% higher than normal, according to Rysted Energy AS.
Compounding the problem is China’s decision to lock down its steelmaking hub of Tangshan in an effort to control a Covid-19 outbreak.
“There are surging costs in the supply chain for all steel products in Europe,” said James Ley, senior vice president for Energy Metals at Rystad.
Copper is another vital ingredient, with high conductivity that’s ideal for internal wiring and external cables. Europe requires about 7.7 million tons to meet its 2030 target, and this year’s rally adds about $7.6 billion to the price tag, according to Bank of America Corp.
Then there’s the aluminium needed for solar panels, turbines and the grids they connect with. Europe has a critical shortage because production dropped after soaring power costs reduced smelting profits.
Russia is the largest producer outside China, with its refined aluminium accounting for about 5% of global production. The market already was tight going into this year, according to BloombergNEF, and prices rocketed to a record in March. The risk that Russia’s shipments could be throttled by potential sanctions helped fuel those increases.
“The world might have to get by without Russian supplies,” Andrew Forrest, chairman and founder of Fortescue Group Metals Ltd., said in an interview. “It is certainly doable, but there’ll be an adjustment period.”
More grids will be needed to deliver huge amounts of renewable generation to where the electricity is needed. About $1.5 trillion in cumulative investment from 2020 to 2050 is needed to add new connections, according to BNEF.
But it’s not just about clean infrastructure. LNG is getting a boost with Germany’s plans for two new terminals as soon as this year and the Netherlands securing a floating storage and regasification unit in March. Italy and Estonia are pushing to swiftly set up theirs, too.
The UK and France are plotting a vast expansion of nuclear power. About 230,000 tons of steel reinforcement will be used in building Electricite de France SA’s Hinkley Point C in southwest England, and plans are being rolled out for another reactor of the same design.
“Everyone is talking about accelerating the energy transition, and everyone will need the same materials,” said Julian Kettle, senior vice president for metals and mining at Wood Mackenzie Ltd.