Fugro has completed work on the burial of export cables at the Gemini offshore wind park, off the Netherlands coast.
The company was awarded the contract by Van Oord in April and mobilised one of its two Q1400 trenching spreads onto the Van Ooord support vessel Jan Steen to execute the export cable burial works.
The scope consisted of burying the deepwater sections of two export cables and one connector cable with a total combined length of 140kilometres, to target depth below seabed level of 1.5metres.
Fugro project manager Glenn Munachen said: “Successful completion of this export cable burial reinforces the capability of the trencher on long distance jetting projects as well as its ability to perform projects in harder ground utilising the Q1400 jetting skid.”